Tuesday, 26 August 2008
26th August 2008 - The build so far
Monday, 25 August 2008
25th August 2008 - Front floor section complete
Sunday, 24 August 2008
24th August 2008 - Cockpit Floor
Spent more time working on the two sections of the cockpit floor. The front section was match drilled to the tabs but still needs the clinchnuts fitting to the tabs and the holes in the floor drilling out for the M4 screws. The bigger task on this section was to measure out and cut the holes for the brake master cylinders and the rudder torque tube carry through. This took two goes and a wasted piece of aluminium but they are now correctly positioned and the rudder and brakes work without any interference. There is still a box to be constructed to fill the hole where the rudder torque tube carry through goes to avoid everything in the cockpit disappearing into the sub floor.
The rear section of the floor is now complete with holes drilled for the rudder cables and glands installed. Also a collar has been made which will carry the control column boot. This can be seen screwed to the floor round the control column torque tube .
The rear section of the floor is now complete with holes drilled for the rudder cables and glands installed. Also a collar has been made which will carry the control column boot. This can be seen screwed to the floor round the control column torque tube .
Friday, 22 August 2008
21st August 2008 - Tabs 41 - 119
Wednesday, 20 August 2008
20th August 2008 - Cockpit floor
Monday, 18 August 2008
18th August 2008 - Left Door Latch
Then fabricated the latch for the left door. Two pieces of 3/8" * 0.058" tubing are welded to the door frame to create the pivot for the handle and the guide for the latch pin. The handle itself is fabricated from 1/4" * 0.035" tubing with a loop on the outside and a simple handle on the inside - why? who knows? but it's what the plans say. I haven't bent the tubing to form the internal handle yet so I can remove the mechanism from the pivot to clad the outside of the door with aluminium as required. A lever was fabricated from 0.071" 4130 plate and this was connected to the latch pin with some 1/16" wire. Some 3/8" channel is used to hide the mechanism from the inside and create the end stops for the travel of the mechanism. Finally a tab was welded to the frame to hook the return spring onto which keeps the latch pin closed unless the handle is turned. All very simple and works well but takes a few minutes to get everything aligned.
17th August 2008 - Seat Bottoms
Saturday, 16 August 2008
15th August 2008 - Rest day
14th August 2008 - Left door
Then a final ream of the sockets to clear any weld penetration and the undercarriage mount is complete.
Then decided to make a start on one of the doors. I'm putting off building the second of paired items so the aircraft has currently one horizontal stabiliser, one elevator, and now one door.
The door was constructed in situ using clamps and 1/4" spacers to position the tubing away from the door frame. This will allow the door to open freely and give space for some sort of seal to be attached to the edge of the aluminium door skin which will overlap the fuselage. As each piece of tubing was cut it was welded to the previous piece with as much of the weld as possible completed so that no change in dimension or shape would take place when final welding Once the complete door framework was completed it was removed for completing the welding and adding the hinge pieces to the front tube. Next step will be to add the hinges to the front of the door frame. The positioning of these will be critical to getting the door to shut whilst exactly overlapping the aluminium cladding of the front section of the fuselage.
Wednesday, 13 August 2008
13th August 2008 - On Wheels!
A 1/4" pilot hole was drilled through the reinforcing tubing and the front of each socket where the 5/16" undercarriage retaining bolt would eventually go. These were aligned horizontally with the spirit level. A line was then drawn mid way up the top bearing surface of the leg so that this could be centred in the pilot hole. The fuselage was then placed on its right side and levelled fore and aft. The left undercarriage leg was then inserted and twisted to get the axle 1 degree from vertical using the digital level - this gives the required amount of wash-in for the wheel. the leg was then

There is still a bit of welding to do to fasten the undercarriage sockets into the reinforcing tubes but that's a job for another day.
Tuesday, 12 August 2008
12th August 2008 - Tabs 1 - 40
Monday, 11 August 2008
11th August 2008 - Fin rework
http://tailwindbuild.blogspot.com/2008/07/24th-july-2008-fin-complete.html
Discussing this on the Yahoo Tailwind forum led to the conclusion that I had under bent the ribs leaving them in tension so when they were heated whilst brazing they bent at the heated points and returned to straight between them. This will be something to watch when I do the horizontal stabilisers and wing tips.
To improve the profile of the fin, I decided to add a thin layer of resin and micro-balloons which could be sanded to a smooth curve. First the channels were roughened with the sand-paper to provide a key for the resin. Then two pieces of scrap aluminium with the protective plastic still on to act as a non-stick membrane were used as "shuttering" held on with spring clamps and a stiff mix of resin and micro-balloons added where required.
Once dry the filler was sanded to profile to produce the smooth curve required.
Whilst I had the filler out, the joints between the rear of the ribs and the trailing edge were also filled to remove the lip caused by the thickness of the folded trailing edge and the joint between the trailing edge and the tail-light fitting faired in. Should get a nice smooth covering now.
10th August 2008 - A "serious" bending brake
The sheet of metal is placed on the table, and the clamp is tightened to hold the sheet in place. The apron is then lifted to bend the metal. The starting point was the plans available on the
But I needed something longer and stronger so the materials were significantly scaled up. The apron and the table are made from 40" lengths of mild steel angle iron 120mm x 75mm x 10mm. The clamp is made from a length of mild steel angle iron 80mm x 80mm x 10mm. The hinges were cut out from 1/2" thick steel plate and the hinge pins were cut from a length of 3/4" steel rod, 3/4" *0.058" tubing provides the sockets for
The outer part of the hinges which attach to the table were final welded together as per the Miller approach. The hinge pins were pushed into place using the vice and assembled with the inner part of the hinge which attaches to the apron. A section of the edge of the table around the hinge pivot was ground down slightly (about 1/50") to provide clearance and the apron itself reduced in length by about 1/100" to allow the two halves of the hinges to turn without binding. Then the table and apron were then clamped together in alignment and the hinges positioned and tack welded. Then it was a case of final welding the hinges into position. This is the first time I've had to turn the welding machine up but 150amps worked well getting good penetration into the thick metal.
I decided to use the angle iron for the clamp sitting on it's open edges so the bottom of the two sides were ground flat to provide a good contact area with the material to be bent. The edges of the clamp were then shaped to provide two different bending radius. Sections of box steel sawn in half were then welded to the top and into the ends to provide horizontal clamping positions. Finally, some scrap angle iron was welded to the bottom of the table to space it off the bench and provide space for the G clamps used to fasten the clamp onto the table and the tubing used to make sockets for the handles welded into place.
As a test, a 12" length of 0.071" steel was bent to make a blank for one of the spar attach brackets - works well, if it can handle 0.071" steel then 0.050" aluminium should be OK.
Sunday, 10 August 2008
8h August 2008 - Flap and aileron torque tubes
Th
e bronze "oilite" bearings arrived today so I completed the construction of the aileron and flap torque tubes. The bearings as purchased were 30mm OD and 15mm ID. They were drilled out to 18.5mm and then reamed to be a smooth fit on the 3/4" aileron torque tube. Oilite is very strange stuff! As the metal gets hot, oil bubbles out of the porous metal and as you drill it the swarf is like a dirty brown paste but they are self lubricating and they certainly provide a good bearing surface. The end of the flap torque tube was then heated to expand it and the bearing tapped into position (note for future reference - it's also an idea to put bearings in the freezer to
make them contract before fitting). The bronze bearings are at the inboard end with Delrin bearings at the centre and outboard end of the flap torque tube.
An additional bearing was reamed to be a tight fit on the aileron torque tube. This was then cut in half and a piece inserted about 2" into the inboard end of each aileron spar. The aileron torque tube was then inserted into this and the washers made previously inserted at the end. The piece of bearing acted to exactly centralise the aileron torque tube in the spar and by inserting the aileron tube into the flap tube and lining up the two tubes the washer could be tacked in place with everything perfectly lined up. The aileron torque tube was then removed for final welding to avoid damaging the Delrin bearings. I might drill and pin the two tubes together through the piece of oilite bearing as a belts-and-braces measure but haven't decided yet.
An additional bearing was reamed to be a tight fit on the aileron torque tube. This was then cut in half and a piece inserted about 2" into the inboard end of each aileron spar. The aileron torque tube was then inserted into this and the washers made previously inserted at the end. The piece of bearing acted to exactly centralise the aileron torque tube in the spar and by inserting the aileron tube into the flap tube and lining up the two tubes the washer could be tacked in place with everything perfectly lined up. The aileron torque tube was then removed for final welding to avoid damaging the Delrin bearings. I might drill and pin the two tubes together through the piece of oilite bearing as a belts-and-braces measure but haven't decided yet.
Friday, 8 August 2008
7th August 2008 - Setting up the HS incidence and control linkage
Next the elevator pushrod was connected to the control system through to the control column. Although the mechanism worked correctly there was inadequate movement of the elevator - the plans call for 30 degrees up and 25 down. After spending some time pondering this and looking at the options it seemed that moving the control column pivot point forward was the answer. Re-reading the plans made it clear that I didn't have enough horizontal distance between the control pivot point and where the elevator pushrod enters the aileron torque tube. Luckily this wasn't a difficult fix. The pivot hole was re-drilled an inch forward and the original hole plugged with a short piece of 5/16" rod welded into place. The new hole was lined with a piece of 3/8" * 0.028" tube as before. The trim lever rod also had to be lengthened by an inch so a new section was welded in place around a length of 7/16" tube to provide additional strength. Finally the system was re-assembled and I now have 31 degrees up and 25 degrees down - perfect. In addition with the original rework I had done on the system the movement is perfectly smooth, frictionless and without any discernable play - that will do!
Wednesday, 6 August 2008
6th August 2008 - Right Horizontal stabiliser
Subscribe to:
Posts (Atom)