18th May - Build Order (work in progress)
- Install firewall
- Install engine mount and main gear
- Install tailwheel
- Install all cable bushings
- Temporarily install panel and fuel tank
- Install strobe pack
- Install cabling to tail-light/strobe
- Install static port tubing
- Install pitot tube to junction in rear spar cover box
- Install VOR antenna cable to junction in rear spar cover box
- Install GPS, and Comm antenna cables
- Install wing nav light and strobe light cables to junctions in rear spar cover box
- Remove panel and fuel tank
- Install combing and front, left and right side combing trim panels
- Install fuel tank
- Install flap torque tube
- Install flap lever to torque tube pushrod
- Install rear floor panel (rudder cables pass through this)
- Install rudder cables, temporarily install rudder, make off rear ends of cables to length, remove rudder
- Install seat belt shoulder straps
- Install seat bottom centre panel
- Install left and right seat bottoms
- Install outer seat belt lap straps
- Install elevator pushrod
- Install baggage compartment angles
- Install seat side fill panels do not screw into place
- Install rear window sills, do not screw into place
- Install rear window diagonal covers
- Install rear window surrounds, do not screw window surrounds to rear window sills until after fuselage sides are covered
- Install all stringers
- Cover fuselage sides
- Install static ports and connect to static tubing
- Install rear windows
- Complete fuselage covering
- Install brake pipe flexible terminations
- Install brake master cylinders
- Install lower fuselage forward skin
- Install transponder antenna
- Install fuel tank breather outlet and tubing
- Install forward floor panel
- Install rudder pedals
- Connect flexible brake pipes