Then the left side of the vertical stabiliser (VS) was covered. This meets the top decking at a right angle. Many aircraft blend the top deck covering into the vertical stabiliser but the construction of the Tailwind has tubing specifically set to create a right angle joint. Next job is to glue access panels into the VS and the floor to allow the horizontal stabiliser bolts to be installed and to allow the elevator pushrod connection to be made to the elevator horns. Then the right side of the rudder can be completed.
Wednesday, 21 September 2011
21st September 2011 - Covering underway
Then the left side of the vertical stabiliser (VS) was covered. This meets the top decking at a right angle. Many aircraft blend the top deck covering into the vertical stabiliser but the construction of the Tailwind has tubing specifically set to create a right angle joint. Next job is to glue access panels into the VS and the floor to allow the horizontal stabiliser bolts to be installed and to allow the elevator pushrod connection to be made to the elevator horns. Then the right side of the rudder can be completed.
Tuesday, 20 September 2011
19th September 2011 - Putting it all together
The interior photo shows how the flap and aileron pushrods pass through the windowsills in the baggage compartment. The edges of the holes are lined with Rayrim edging. This is ready glued and is installed with a heatgun neatly protecting the edges.
Last job for the day was to set up a 8x4 workbench in the garage, remove the wheels, and carry the fuselage into the garage and put it on the bench ready for starting covering. I haven't weighed the fuselage in its current state but carrying it was just possible with two people and I can just about rotate it on the bench by myself.
Friday, 16 September 2011
15th September 2011 - Back from sand blasting
Monday, 5 September 2011
5th September 2011 - Baggage Compartment
Friday, 2 September 2011
2nd September 2011 - Plumbing the vacuum system and installing the coaming
1st September 2011 - Terminating the rudder cables
Wednesday, 31 August 2011
31st August 2011 - Fuel tank installation