The last few days have been an endless round of spray, sand, fill, re-sand, respray but finally the cowls are ready for top-coating - not perfect but perfectly acceptable. Hopefully the top-coat will go on OK without too many embedded insects!
Friday, 24 April 2015
Thursday, 16 April 2015
15th April 2015 - Finishing painting and re-installing the engine
The extra paint arrived this morning so I could complete the painting of the engine. Then I started to re-install the ancillaries doing as much as possible before re-mounting the engine to make access easy.
The engine hoist was then positioned to allow the engine to be bolted back onto the mount. Parallel mount engines are so much easier than dynafocal!
Once back on the airframe the baffles were re-installed and the rest of the plumbing started. I've still got the exhausts and carburettor to go back but things are looking good so far.
That is one more line in the final to-do list ticked off - only took 3 days of solid work!
The engine hoist was then positioned to allow the engine to be bolted back onto the mount. Parallel mount engines are so much easier than dynafocal!
Once back on the airframe the baffles were re-installed and the rest of the plumbing started. I've still got the exhausts and carburettor to go back but things are looking good so far.
That is one more line in the final to-do list ticked off - only took 3 days of solid work!
Tuesday, 14 April 2015
14th April 2015 - Painting the engine
Baffles
Magnetos
Vacuum pump
Carburettor
EGT sender
CHT sender
Carburettor temperature sender
Starter motor
Alternator
Primer lines
Exhaust system
Flywheel
Propeller extension
RPM sender
Oil pressure takeoff
Earth strap
Fuel overflow
Fuel inlet
Fuel pump outlet
Engine breather
Heater scat tube
Multiple cables fastened to the sump attach bolts
and finally - the engine mount bolts
With the engine removed I could touch up the accumulated scratches and chips on the engine mount paint. The engine itself is substantially finished but 2 rattle cans is not enough so further progress is on hold waiting for an extra can.
Friday, 10 April 2015
10th April 2015 - It is officially spring, let work on G-CIJY recommence
Finally some warm dry weather to get going again on the build.
First job was to refit the propeller and do an engine run to check the compressions. The Odyssey PC680 battery showed no signs of deterioration despite being left untouched for 5 months. The same couldn't be said of the left magneto which needed the points drying before it felt like starting the engine. However, once it was cleaned and re-timed the engine started immediately and ran smoothly.
I borrowed a calibrated differential compression tester from my local aircraft engineering company and with the engine warm checked the compressions:
I also used the engine runs to tweak the vacuum regulator. This put the vacuum nicely into the green arc so the DI and AI should work well. It also proved that the vacuum pump is operating properly.
Next the transponder was re-installed after repair and this time its Mode S code could be configured as the aircraft is now registered with the CAA!
G-CIJY may not be the most interesting call sign but by choosing an in-sequence registration it saved a significant chunk of money compared to a "personalised" registration.
Much of the remaining work on the aircraft is now in the category "finishing" and the next job is to remove the engine, touch up the mount, paint the engine, and refit it ready for flight.
First job was to refit the propeller and do an engine run to check the compressions. The Odyssey PC680 battery showed no signs of deterioration despite being left untouched for 5 months. The same couldn't be said of the left magneto which needed the points drying before it felt like starting the engine. However, once it was cleaned and re-timed the engine started immediately and ran smoothly.
I borrowed a calibrated differential compression tester from my local aircraft engineering company and with the engine warm checked the compressions:
- 73/80
- 73/70
- 75/80
- 74/80
I also used the engine runs to tweak the vacuum regulator. This put the vacuum nicely into the green arc so the DI and AI should work well. It also proved that the vacuum pump is operating properly.
Next the transponder was re-installed after repair and this time its Mode S code could be configured as the aircraft is now registered with the CAA!
G-CIJY may not be the most interesting call sign but by choosing an in-sequence registration it saved a significant chunk of money compared to a "personalised" registration.
Much of the remaining work on the aircraft is now in the category "finishing" and the next job is to remove the engine, touch up the mount, paint the engine, and refit it ready for flight.
Subscribe to:
Posts (Atom)